Canadian mast climber manufacturer Fraco Products has won a
contract valued at more than US$7 million to supply as many as
74 mast climbing work platforms to subcontractors working on the
massive Barwa Commercial Avenue mega project in Doha, Qatar.
Fraco's platforms have been selected by Alumco Qatar and Reem
Emirates Aluminum LLC, the façades sub-contractors who
will provide aluminum cladding, curtain walls and glazing works
on the 8 km long façade. The main contractor on the project
is Hochtief Construction Qatar.
The contract calls for the supply of 20 ACT-8 platforms - Fraco's
most popular platform -followed by a further 54 units by July
2010. At the peak of the project, Fraco platforms will be used
by up to 750 people.
Armand Rainville, chairman of Fraco, said; "The agreement
is the result of two years of tireless efforts by our dealer in
Qatar, SkyClimbers Limited, to position Fraco's equipment in the
Arabian Peninsula.
"Being involved in the development boom of Doha is an
incredible opportunity for our company. In fact, that project
is consequent with our geographical market development strategy,
and is in accordance with our market segmentation approach which
target commercial, industrial, oil and gas, and industrial areas."
The Barwa Commercial Avenue project is located in the southern
outskirts of Doha, and is a mixed development with 600 retail
spaces, 850 residential units and offices, and various service
centres and amenities.
The first 20 platforms will be used on a 2.2 km segment of
the project where Alumco Qatar will install 31000 m2 of aluminium
cladding and 48500 m2 of stick system curtain walls, windows and
doors. This portion of works should start in April 2010 and will
be complete by mid 2011. The other subcontractor, Reem Emirates
Aluminum, will be responsible for other building types.